Traction Transformers: Single-Phase Scott and V Connections

Publisher · Henan Chuangwit Railway Equipment Co., Ltd.   Updated ·

A traction transformer is the substation unit that steps transmission grid voltage down to traction feeding voltage. On a plain 25 kV line it delivers single-phase power between catenary and rail; on 2x25 kV autotransformer feeding it supplies 50 kV between the catenary at +25 kV and a negative feeder at -25 kV (California High-Speed Rail guideline TM 3.1.1.1). Scott and V connections organise these single-phase outputs so the three-phase grid sees a more balanced load.

Large traction transformer in substation hall with bushings

Key Takeaways

  • Traction load is single-phase; single-phase, V and Scott arrangements differ only in how they distribute that load across the three grid phases.
  • A plain 25 kV substation transformer feeds catenary to rail, while a 2x25 kV installation supplies 50 kV between catenary and negative feeder, with autotransformers every 10 to 15 km keeping the train side at 25 kV (California High-Speed Rail guideline TM 3.1.1.1).
  • Booster transformer feeding inserts series transformers in the catenary and return conductor loop instead of raising substation voltage.
  • Substation switchgear around the transformer includes vacuum circuit breakers tested within GB/T 1984 with GB/T 11022 common requirements, and disconnectors to GB/T 1985-2023 with TB/T 2803-2003.
  • Catenary-side disconnectors typically rate 27.5 kV and 1250 A on copper alloy contacts, per GB/T 1985-2023 construction practice.

What is a traction transformer and what makes it special?

Power transformers in general feed balanced three-phase loads. A traction transformer feeds the most unbalanced load on the grid: single-phase traction current between one conductor and an earthed return, varying from zero to full rating as trains accelerate. The design consequences are repeated short-time overloads, harmonics from the rolling stock converters, and a mechanical duty that follows traffic rather than a steady profile.

Rating philosophy follows that duty. A traction transformer is sized for the traffic cycle of its arms, meaning repeated short-time overloads rather than one continuous figure, and its impedance is chosen to share load sensibly between substations while keeping voltage regulation on the arms acceptable. Cooling, tap ranges and the harmonic content the converter fleets impose all enter the specification alongside the connection diagram, which is why the transformer data sheet is thicker than the single line diagram suggests.

The connection chosen at the substation decides how that single-phase load projects onto the three-phase grid. One transformer on one phase pair gives maximum imbalance; two transformers on two different phase pairs, the V connection, share it; the Scott connection arranges two single-phase outputs in electrical quadrature so that, loaded equally, the pair draws symmetrically from all three grid phases. No connection removes imbalance, each only manages it.

How do single-phase, V and Scott connections differ?

Picture a substation feeding two catenary arms in opposite directions, the standard layout. The table compares the three classic arrangements for that job.

ConnectionArrangementGrid-side effectTypical use
Single-phaseOne transformer across one phase pair feeding one or two armsLargest voltage imbalance and negative-sequence currentSmall terminals, one-arm feeding
V connectionTwo single-phase transformers on two phase pairs sharing the substationLoad split over two phase pairs, residual imbalance remainsTwo-arm substations built in stages
Scott connectionTwo transformers arranged for outputs in electrical quadratureBalanced three-phase draw when both arms carry equal loadTwo-arm substations near weak grid points

The choice follows the strength of the feeding grid point and the traffic on each arm. Where both arms run similar timetables, the Scott arrangement keeps the draw symmetric; where one arm is a lightly used branch, the symmetry buys less and the simpler V or single-phase arrangement often wins on cost and internal losses.

Diagrams of single-phase V and Scott connections feeding two catenary arms
Connection arrangements of traction transformers feeding two catenary arms; feeding voltages per guideline TM 3.1.1.1

What does a traction substation single line diagram show?

The single line diagram is the map of the installation: an incoming grid bay with its disconnectors and protection, the traction transformer or transformer bank, low-voltage busbars, and outgoing feeder bays, one per catenary arm, each with its circuit breaker, disconnector, metering and protection. Earthing and the connection to the return circuit complete the picture.

Reading it from the grid down tells the procurement story: breaker duty within the GB/T 1984 family with GB/T 11022 common requirements, disconnectors built to GB/T 1985-2023 with electric control to TB/T 2803-2003, and catenary-side ratings that typically reach 27.5 kV and 1250 A rated normal current on copper alloy contacts. The switching chain around the transformer, and how those devices differ, is unpacked in our article on disconnectors, switch disconnectors and circuit breakers; the fault-clearing side continues in our piece on vacuum circuit breakers for traction power.

Protection completes the reading. Feeder protection must cover faults along the whole arm while discriminating against inrush and through-load, and the diagram marks where current and voltage information comes from for each relay. The same sheet shows the earthing transformer arrangement, where fitted, that limits earth-fault levels, and the point at which the return circuit connects into the substation earth mat, the interface that the earthing rules of EN 50122-1 govern.

How does the transformer interact with AT or BT feeding?

The substation transformer voltage is set by the feeding scheme. The table gathers the verified arrangements.

Feeding arrangementTransformer output (kV)Train-side voltage (kV)Line hardware
Plain 25 kV25, catenary to rail25Catenary only
2x25 kV autotransformer50, between catenary at +25 kV and negative feeder at -25 kV25, catenary to rail at autotransformer pointsNegative feeder plus autotransformers about every 10 to 15 km
Booster transformer25, catenary to rail25Return conductor plus series booster transformers

Source: California High-Speed Rail traction power design guideline TM 3.1.1.1 and an IIT Comillas 2x25 kV planning study; booster arrangement per traction feeding practice.

The interaction runs both ways. Autotransformer feeding lets a substation feed longer arms because bulk energy moves at the higher voltage, so the Scott or V layout at one substation covers more route; booster feeding keeps the transformer a plain 25 kV unit and moves the engineering into the series devices along the line. The full trade is set out in our autotransformer versus booster transformer comparison.

For 2x25 kV schemes the substation transformer works in partnership with the line autotransformers: the substation unit supplies the 50 kV loop, and the line devices convert it back to 25 kV for the train at their centre taps. Specifying one without the loading pattern of the other is how a scheme ends up with autotransformers sized for traffic that never runs, or starved on the busiest day of the year.

What should specifiers check around the transformer package?

Four checks recur in review. Impedance and voltage regulation against the arm length, since the train must still see usable voltage at the far end; overload duty matched to the traffic pattern the timetable implies; the connection arrangement agreed with the grid operator, because imbalance limits are theirs to set; and the switchgear envelope, meaning breaker standards, disconnector ratings and earthing, specified together with the transformer rather than after it.

Feeder bays also connect downstream to the feeding and sectioning posts that subdivide each arm, and the whole chain from grid to pantograph is walked through in our overview of the grid-to-pantograph power chain. For rating and symbol questions on the disconnectors in those bays, our railway disconnector FAQ collects the common answers.

Frequently Asked Questions

What is a traction transformer?

The transformer in a traction substation that steps the transmission grid voltage down to traction feeding voltage. On plain 25 kV lines it feeds single-phase power between catenary and rail; on 2x25 kV autotransformer feeding it supplies 50 kV between catenary and negative feeder while autotransformers every 10 to 15 km keep the train side at 25 kV, per the California High-Speed Rail guideline TM 3.1.1.1.

What is a traction substation?

The installation where the public grid meets the railway: grid-side bays, the traction transformer, busbars and outgoing feeder bays with circuit breakers and disconnectors feeding the catenary arms. Breakers fall under the GB/T 1984 family with GB/T 11022 common requirements, disconnectors under GB/T 1985-2023 with TB/T 2803-2003, and catenary-side ratings typically reach 27.5 kV and 1250 A.

What does a traction substation single line diagram show?

The electrical map of the substation on one sheet: the incoming grid connection, the transformer or transformer bank with its connection arrangement, low-voltage busbars, and one outgoing bay per catenary arm containing the circuit breaker, disconnectors, metering and protection, plus earthing and the return circuit connection. It is the document against which protection settings and feeder ratings are checked.

Why are Scott and V connections used in traction substations?

Because traction load is single-phase and the grid is three-phase. A V connection spreads the load over two phase pairs; a Scott connection arranges two single-phase outputs in electrical quadrature so that, with both feeding arms equally loaded, the three-phase side draws symmetrically. Both limit the imbalance a single transformer on one phase pair would impose on the supplying grid.

Specifying the Substation Core

The traction transformer is where the railway negotiates with the grid: the connection arrangement manages imbalance, the voltage class follows the feeding scheme, and everything downstream, arms, neutral sections, feeding posts, inherits those decisions. Fix the feeding scheme first, the connection second, and the switchgear envelope together with both.

For questions on how these arrangements interact with the overhead hardware your project specifies, talk to our engineering team.

Need a quotation, datasheet or custom solution?